Sourcengine
Sourcenginebreadcrumb separatorResource Articlesbreadcrumb separatorIndustry Newsbreadcrumb separator
Wayward balloon causes brief power outage affecting multiple European chipmakers

Wayward balloon causes brief power outage affecting multiple European chipmakers

A person shines a flashlight on a circuit breaker in a darkened area.

Last month, a wayward balloon caused a 20-minute power outage in Dresden, Germany, after coming into contact with a city power substation. As a result, local Infineon Technologies and Bosch microchip factories lost power and briefly suspended production. The stray balloon also affected work a GlobalFoundries fab in the region.

The German power disruption could exacerbate existing procurement problems caused by the global chip shortage.

One Balloon Interrupts the Operations of Dresden’s Chip Manufacturers

On September 17, a foil balloon floated in-between two live conductors at a Dresden substation, which prompted a short circuit. That incident caused a widespread power outage in the city that created big problems at local semiconductor plants.

Infineon shuttered its Dresden facility for four days following the incident. When operating normally, the complex fabricates over 400 different parts using 200mm and 300mm nodes. Its focus had been on producing payment card, security, and automotive products. The factory, one of chipmaker’s largest, employs 2700 workers and uses Industry 4.0 technology to optimize its output.

Infineon directed its Dresden location to silicon wafers, PMICs, MCUs, and MOSFETs.

Bosch’s state-of-the-art $1.2 billion chip plant also ceased operations following the electricity disruption. The leading car parts vendor opened the complex six months ahead of schedule in July to address the global chip shortage. The factory normally manufactures wafers, ASICs, and power semiconductors with automotive applications.

As of this writing, neither company has detailed how the power failure will impact their output or lead times.

GlobalFoundries, the world’s largest foundry service provider by revenue, also operates a plant in the area impacted by the balloon accident. Since the contract chipmaker maintains two on-site energy facilities, the outage did not prompt a production shutdown. However, the blackout had “some limited impact” on the fab because it does use some municipal electricity,

GlobalFoundries spokesperson Erica McGill said the event had strengthened the company’s resolve to make the fab “completely independent of the public grid.”

Recent Developments Have Worsened the Global Chip Shortage

Unless one of the affected chipmakers states otherwise, the brief Dresden power outage should not significantly impact the worldwide electronic components supply chain. The brevity of the event and its relatively small impact area should not create waves on a global scale. That said, the timing of the outage could not have been worse, as the industry has been grappling with shortages since December 2020.

Since then, two unforeseeable events have made the microelectronics bottleneck more severe.

An intense winter and ice storm hit the United States in mid-February, causing hundreds of fatalities and widespread blackouts. The disaster overwhelmed the Texas power grid and prompted local utility providers to ask heavy power users to close temporarily. Samsung, Infineon, and NXP Semiconductors abruptly shuttered their Austin area locations in response and reopened them a month later.

However, the storm cost the three chipmakers hundreds of billions of dollars in ruined materials and lost fabrication time.

In addition, a fire broke out at a Naka, Japan-based manufacturing facility owned by Renesas Electronics. The blaze destroyed 23 pieces of production equipment and contaminated 6,400 square feet of clean room space. The corporation responded proactively and re-tasked 70 percent of its orders to its other fabs.

The plant returned to 95 percent capacity in July, but its production layoff further constrained the global supply of automobile MCUs.

The fire in Japan and the ice storm in Texas contributed to average semiconductor turnaround times reaching a record 21.7 weeks. Over the next few years, the industry’s leading providers will establish new capacity to relieve the bottleneck. But until then, OEMs, CMs, and EMS providers will have to deal with pricing volatility and availability problems.

As such, manufacturers would benefit from bringing Sourcengine into their supply chains. The global e-commerce marketplace hosts listings from over 3,000 factory direct and thoroughly vetted vendors. It can also ship electronic components with any geographical restrictions.

Quotengine: Your Ultimate BOM Tool
With Quotengine’s real-time data on over 1 billion part offers, managing your BOM effectively has never been simpler.
Upload Your BOM
What’s Your Excess Worth?
Real-time market data, quick response time, and unique price offers to help you maximize your return on excess inventory.
Get an Estimate
The Last Integration You’ll Ever Need
Streamline manual processes and gain real-time access to inventory data, pricing updates, and order tracking through Sourcengine’s API
Sign-up Here
Sourcengine’s Lead Time Report
Strategize for upcoming market shifts through lead time and price trends with our quarterly lead time report.
Download now
Sourcengine’s Lead Time Report
Strategize for upcoming market shifts through lead time and price trends with our quarterly lead time report.
Download now